|
Home DBE Program DBE Final Rule
DBE Final Rule
Prev | Index | Next
Section 26.29 What Prompt Payment Mechanisms Must Recipients Have?
Question And Answer
There was substantial comment on the issue of prompt payment. A
majority of commenters supported the concept of prompt payment
provisions. Some recipients pointed out that they already had prompt
payment provisions on the books. DBEs generally supported mandating
prompt payment provisions though they, as well as other commenters,
recognized that slow payment is a problem affecting many
subcontractors, not just DBEs. Some of these comments suggested making
prompt payment requirements applicable to subcontracts in general, not
just DBE subcontracts. Some recipients were concerned about getting in
the middle of disputes between prime contractors and subcontractors.
Some commenters wanted the Department to mandate prompt payment
provisions, while others preferred that their use by recipients remain
optional.
Having considered the variety of views expressed on this subject,
the Department believes that prompt payment provisions are an important
race-neutral mechanism that can benefit DBEs and all other small
businesses. Under part 26, all recipients must include a provision in
their contracts requiring prime contractors to make prompt payments to
their subcontractors, DBE and non-DBE alike. It is clear that DBE
subcontractors are significantly--and, to the extent that
they tend to be smaller than non-DBEs, disproportionately--affected by
late payments from prime contractors. Lack of prompt payment
constitutes a very real barrier to the ability of DBEs to compete in
the marketplace. It is appropriate for the Department to require
recipients to take reasonable steps to deal with this barrier. We
recognize that delayed payments do not affect only DBE contractors; a
prompt payment requirement applying to all subcontracts is an excellent
example of a race-neutral measure that will assist DBEs, and we are
therefore requiring that recipients' prompt payment mechanisms apply to
all subcontracts on Federally-assisted contracts.
Paragraph (a) of this section requires recipients to put into their
DBE programs a requirement for a prompt payment contract clause. This
clause would appear in every prime contract on which there are
subcontracting possibilities, and it would obligate the prime
contractor to pay subcontractors within a given number of days from the
receipt of each payment the recipient makes to the prime contractor.
Payment is required only for satisfactory completion of the
subcontractor's work. The clause would also apply to the return of
retainage from the prime to the subcontractor. Retainage would have to
be returned within a given number of days from the time the
subcontractor's work had been satisfactorily completed, even if the
prime contract had not yet been completed. A majority of commenters on
the retainage issue favored a requirement of this kind.
The number of days involved would be selected by the recipient,
subject to OA approval as part of the recipient's DBE program. In
approving these time frames, the OAs will consider whether they are
realistic and sufficiently brief to ensure genuinely prompt payment.
Recipients who already operate under prompt payment statutes may use
their existing authority in implementing this requirement. It may be
necessary to add to existing contract clauses in some cases (e.g., if
existing prompt payment requirements do not cover retainage).
Paragraph (b) lists a series of additional measures that the
regulation authorizes, but does not require, recipients to use. These
include alternative dispute resolution, holding of payments to primes
until subcontractors are paid, and other mechanisms that the recipient
may devise. All these mechanisms could be made part of the recipient's
DBE programs.
Prev | Index | Next
|